Phase 1 (internal works: completed)

On Monday 27 February 2023, Martin signed contracts with builder, plumber and electrician. On Thursday 2 March, work began on the internal works.

Permission

Wiring

Rewire the entire house apart from the bedrooms on the second floor and the completed second floor bathroom. Double universal sockets throughout. Lay tracks for photovoltaics on the roof (hoping that permission will be obtained).

Heating and cooling

Living room (2nd floor)

Strengthen floor, replaster, sandblast ceiling, lay wooden floor.

Kitchenette (2nd floor)

Lavanderia (1st floor)

Bathroom (1st floor)

Kitchen (1st floor)

Bathroom (ground floor)

Sandblasting

In addition to the ceiling of the living room, the following ceilings will be sandblasted:

  • The second floor kitchenette
  • The second floor hallway
  • The top of the stairway
  • A small section on the stairway mid-way between the first and second floors
  • A small section on the stairway mid-way between the ground and first floors
  • The small section of ground floor hallway between the doors to the cantina and bathroom

Flooring

  • Wood floor in living room
  • Repair tiled floor in kitchen
  • Tiled floor for new bathroom on first floor
  • Tiled floor for ground floor bathroom
  • Tile excavated section of the ground floor hallway to match the surrounding floor
  • Renovate the stairs

Decoration

Plaster walls where needed. Redecorate throughout.